High-Level Waste Management at the Savannah River Site
Recommendation
2001-1
2001-1
Document
Closed
Timeline (2001 - 2011)
2011
Closed
December 7, 2011
January 28, 2011
2010
Implementation Plan
November 24, 2010
2009
2008
2007
2006
DOE Implementation Plan Received
July 11, 2006
2005
2004
2003
2002
DOE Implementation Plan Approval
June 27, 2002
January 29, 2002
2001
December 13, 2001
DOE Implementation Plan Due
September 17, 2001
September 14, 2001
Public Comment on DOE Response Due
July 18, 2001
DOE Response Printed in Federal Register
June 18, 2001
DOE Response Received
May 21, 2001
DOE Response Due
May 18, 2001
Public Comment Due
May 3, 2001
Recommendation Printed in Federal Register
April 3, 2001
Recommendation Delivered to DOE
March 23, 2001
Key Information
DNFSB Staff Contact |
Ben Heshmatpour
|
---|---|
DOE Responsible Manager |
James Owendoff
|
DOE Issue Lead |
Steven Petras
|