Prioritization for Stabilizing Nuclear Materials
Recommendation
2000-1
2000-1
Document
Closed
Timeline (2000 - 2013)
2013
Closed
December 19, 2013
2012
2010
2009
2008
2007
2006
DOE Implementation Plan Approval
January 5, 2006
2005
DOE Implementation Plan Received
December 1, 2005
2004
2003
2002
Implementation Plan
July 22, 2002
February 26, 2002
2001
January 19, 2001
2000
September 27, 2000
DOE Implementation Plan Due
June 26, 2000
Public Comment on DOE Response Due
April 26, 2000
DOE Response Printed in Federal Register
March 27, 2000
DOE Response Due
March 16, 2000
DOE Response Received
March 14, 2000
Public Comment Due
February 25, 2000
Recommendation Printed in Federal Register
January 26, 2000
Recommendation Delivered to DOE
January 14, 2000
Key Information
DNFSB Staff Contact |
David Gutowski
|
---|---|
DOE Responsible Manager |
James Owendoff
|
DOE Issue Lead |
Steven Petras
|