Criticality Safety at the Department of Energy's Rocky Flats Plant
Recommendation 1990-6
Document
Closed
Timeline (1990 - 1995)
1995
Closed
October 24, 1995
1991
March 14, 1991
1990
DOE Implementation Plan Approval
December 3, 1990
DOE Implementation Plan Received
November 30, 1990
Implementation Plan
November 29, 1990
DOE Implementation Plan Due
October 24, 1990
Public Comment on DOE Response Due
August 27, 1990
DOE Response Printed in Federal Register
July 26, 1990
DOE Response Received
July 24, 1990
Public Comment Due
July 11, 1990
Recommendation Printed in Federal Register
June 11, 1990
Recommendation Delivered to DOE
June 5, 1990