Restart of the K, L, and P Reactors at Savannah River Site

Recommendation 1990-1

Timeline (1990 - 1992)

1992

Closed
October 27, 1992

1991

1990

DOE Implementation Plan Approval
November 28, 1990
DOE Implementation Plan Received
July 13, 1990
Implementation Plan
Public Comment on DOE Response Due
May 14, 1990
DOE Response Due
April 15, 1990
DOE Response Printed in Federal Register
April 13, 1990
DOE Response Received
April 10, 1990
Public Comment Due
March 31, 1990
Recommendation Printed in Federal Register
March 1, 1990
Recommendation Delivered to DOE
February 22, 1990