Recommendation 1992-1

Timeline (1992 - 1993)

1993

DOE Implementation Plan Due
February 4, 1993

1992

Public Comment on DOE Response Due
December 7, 1992
DOE Response Printed in Federal Register
November 6, 1992
Closed
October 27, 1992
DOE Response Received
October 20, 1992
DOE Response Due
October 14, 1992
Public Comment Due
June 29, 1992
Recommendation Printed in Federal Register
May 29, 1992
Recommendation Delivered to DOE
May 21, 1992